Timeline
De Francesco Renovations |
||
October 30, 2018 Last Updated: April 26, 2018 | ||
Year | Months | |
Dept. of General Services Architect/Engineer Advertise & Selection | 2018 | August to December |
Contract Negotiation & Approval | 2019 | January to March |
Project Design | 2019 - 2020 | April 2019 through June 2020 |
Contractor Prequalification | 2019 | August to Nov |
Invitation for Bid, Bid & Award | 2020 | July to August |
Construction Contract Approvals | 2020 | September to December |
Prep Work Old Main 4th & 5thFloors | 2021 | January to May |
Staff Relocation to Old Main | 2021 | May |
De Fran Construction | 2021-2022 | June 2021 to November 2022 |
Furniture, Fixtures & Equipment Delivery & Install | 2022 | October to November |
Staff Relocation to DeFran | 2022-2023 | December 2022 to January 2023 |
Building Open for Classes | 2023 | January |