Timeline

De Francesco Renovations 


October 30, 2018                                                                              Last Updated: April 26, 2018
  Year Months
Dept. of General Services Architect/Engineer Advertise & Selection 2018 August to December
Contract Negotiation & Approval 2019 January to March
Project Design 2019 - 2020 April 2019 through June 2020
Contractor Prequalification 2019 August to Nov
Invitation for Bid, Bid & Award 2020 July to August
Construction Contract Approvals 2020 September to December
Prep Work Old Main 4th & 5thFloors 2021 January to May
Staff Relocation to Old Main 2021 May
De Fran Construction 2021-2022 June 2021 to November 2022
Furniture, Fixtures & Equipment Delivery & Install 2022 October to November
Staff Relocation to DeFran 2022-2023 December 2022 to January 2023
Building Open for Classes 2023 January